Design, manufacturing, testing and installation of a system composed by two independent cars with storage support.
Initial situation description
Extremely difficult transportation of the wind towers plate roll (external diameter between 2.000 mm and 4.500 mm) across the production area.
Need to solve
Main problem was that the ferrule needed to be removed from the production unit, at a different height, and transported 60 meters.